Complete Demolition of 8 existing buildings to make way for new UTSW Hospital Campues.
-
Demolition of 5 Story Building, 4 Story Building and single story data center and surrounding
commercial structures in Phase 1 simultaneously on a 40 day schedule, which Precision completed 4
days early. -
Phase 1 consisted of 300,000/sqft of structure demolition.
-
Phase 2 consisted of complete
demolition of 4 story concrete structure of 230,000/sqft and surrounding building structures.
![IMG_6911](https://static.wixstatic.com/media/0f2c04_a7e5ec3d9fa24ea0bd8426b0ea0ecc90~mv2_d_2592_1936_s_2.jpg/v1/fill/w_147,h_110,al_c,q_80,usm_0.66_1.00_0.01,blur_2,enc_avif,quality_auto/0f2c04_a7e5ec3d9fa24ea0bd8426b0ea0ecc90~mv2_d_2592_1936_s_2.jpg)
IMG_6911
![DSC_0573](https://static.wixstatic.com/media/0f2c04_2475ca08badd4722aba335969ad31bed~mv2_d_6016_4000_s_4_2.jpg/v1/fill/w_147,h_98,al_c,q_80,usm_0.66_1.00_0.01,blur_2,enc_avif,quality_auto/0f2c04_2475ca08badd4722aba335969ad31bed~mv2_d_6016_4000_s_4_2.jpg)
DSC_0573
![DSC_0561](https://static.wixstatic.com/media/0f2c04_e46a1a30f0934f139e04a05da2536bdb~mv2_d_6016_4000_s_4_2.jpg/v1/fill/w_147,h_98,al_c,q_80,usm_0.66_1.00_0.01,blur_2,enc_avif,quality_auto/0f2c04_e46a1a30f0934f139e04a05da2536bdb~mv2_d_6016_4000_s_4_2.jpg)
DSC_0561
![IMG_6911](https://static.wixstatic.com/media/0f2c04_a7e5ec3d9fa24ea0bd8426b0ea0ecc90~mv2_d_2592_1936_s_2.jpg/v1/fill/w_147,h_110,al_c,q_80,usm_0.66_1.00_0.01,blur_2,enc_avif,quality_auto/0f2c04_a7e5ec3d9fa24ea0bd8426b0ea0ecc90~mv2_d_2592_1936_s_2.jpg)
IMG_6911
1/5
bottom of page