Robinson Center

426 West Markham Street

Little Rock, AR 72201

​

  • The demolition work will follow a 4.5 months at the hall schedule with an additional 4 (four) weeks for demolition work
    required in the link.

  • The building demolition will begin with the removal of the existing structures which extend beyond the main structure at the North West areas of the building. This must be removed to facilitate the construction of the concrete brace frames (two (2) weeks)